Who Can Sign Electrical Plans in California

Last reviewed November 9, 2026

​

Who can sign electrical plans in California comes down to one question: will the person who drew them install them? If not, the plans need a registered electrical engineer or an architect. If so, the city can still require an engineer for calculations or larger services. LADBS correction item A.1 names the same three signers: “Registered Electrical Engineer, or Licensed Architect, or Licensed Electrical Contractor (C-10).” Red Dog Engineering is the engineer. Jerry Poon, PE, California #20878, reviews and signs commercial and industrial electrical plans in Los Angeles, Orange, and San Diego counties, remotely, with an electronic seal.

​

Call (626) 428-9005 or email jerry@reddog.engineering with the correction sheet, the checked set, the single-line and panel schedules as they exist, any utility letter, and the job address. You get the scope, the turnaround, and the fee after review. Expedited review is available.

Send the Correction Sheet and the Checked Set

Attach the correction sheet, the checked set, and the job address. You get the scope, the turnaround, and the fee after review. Expedited review is available.

​

Or email directly: jerry@reddog.engineering

What California Law Says About Who Prepares Electrical Plans

In California, a licensed contractor may design electrical systems only “for work to be performed and supervised by that contractor within the classification for which his or her license is issued,” and “nothing in this section is intended to imply that a licensed contractor may design work which is to be installed by another person.” Otherwise, electrical plans are prepared by, or under the responsible charge of, a registered electrical engineer. That is Business and Professions Code section 6737.3, last amended effective January 1, 2004.

​

The state licensing board puts it this way for building officials: a contractor “may only design electrical or mechanical systems which he or she will install. An employee of the contractor may perform the installation. However, the contractor cannot subcontract the installation to another contractor.” (BPELSG, Guide to Engineering & Land Surveying for City and County Officials, Q10.)

​

So the question on a job site is simple. If the C-10 who drew the set is the C-10 pulling the wire, he can sign it. If the set came from someone who will not be installing it: a design-build firm that lost the install, a drafter, or a sub who was replaced, the exemption does not reach it, and the plans need an electrical engineer or an architect.

​

Two separate questions get mixed together here. The state decides who may practice engineering. The city decides what it will accept at the counter, and the Board confirms that “a local agency may adopt ordinances or regulations to require that all engineering documents submitted for review be signed and sealed” (BPELSG guide, Q12). The sections below cover both.

electrical-plan-check-corrections-example.webp

What It Means When an Engineer Reviews and Signs Plans Someone Else Drew

Responsible charge means the engineer “makes or reviews and approves the engineering decisions,” may do so “through the use of communication devices,” and “must be capable of answering questions” about the engineering decisions made during his participation in the project (16 CCR § 404.1(a)(1)(A), (a)(3), (b)). The regulation names the decisions: design standards and methods, materials, and “the preparation of engineering plans, specifications, calculations, reports, and other documents.”

​

In practice that means the engineer reads every sheet he signs, checks the calculations behind it, and marks up what has to change. Los Angeles writes the same thing into its code: when plans do not comply, the changes are made “by the person specified in Subsection (a)” “or by the person’s duly authorized agent” (LAMC 93.0206(d)), so your drafter can carry the redlines under the engineer’s direction. A signature on a set nobody reviewed is not something the regulation allows, and it is not a service we offer.

​

The engineer does not have to take over the whole project. The seal covers the work it is placed on. The regulation requires plans to be signed and sealed so that “all work can be clearly attributed to the licensee(s) in responsible charge” (16 CCR § 411(g)(1)), with a notation describing the work under each licensee’s charge where more than one signs (§ 411(g)(3)). In practice the engineer seals the single-line, the schedules, and the calculations he produced or reviewed, and the sheets say so. Sheets he seals carry his signature, seal, and date on each sheet (B&P 6735.3(a)).​

​

Documents prepared by or under the engineer’s responsible charge carry his name and license number, and interim sets carry a notation such as “for plan check only” (6735.3(a)); the date of signing goes next to the seal (§ 411(h)). Review by communication devices is written into § 404.1(a)(3), which is why this work is done remotely: drawings, calculations, and photos move by email, and nobody waits for a site visit.

​

Who May Sign Electrical Plan-Check Sets in the City of Los Angeles

In the City of Los Angeles, plan-check sets “shall be prepared by and bear the signature and registration number of an appropriate State of California ... Electrical Engineer or Licensed Architect,” except that “a person holding a state license as a contractor who will perform the work” may prepare and sign them for most of the listed cases; “the work must be within the classification for which the license is issued” (LAMC 93.0206(a)). The exception does not reach “engineering calculation(s) and analysis.” When the checker asks for calculations, the answer is an engineer.

​

LAMC 93.0206(b) requires plans “submitted to and approved by the Department before a permit is issued” for listed cases, including “any first-time tenant(s), any installation if the new total connected load exceeds 400 amperes, or the installation of equipment rated 600 amperes or more.” The other listed cases, in plain words: theaters and places of assembly; new buildings or additions over 30,000 square feet; anything over 600 volts; hazardous locations; exit signs, egress lighting, or security lighting; emergency, standby, fire alarm, and gas detection systems; fixtures over 300 pounds; and “engineering calculation(s) and analysis.”

​

The LADBS correction list (Rev. 12/01/2022) is keyed to the 2023 Los Angeles Electrical Code and predates the 2026 code. Its item A.1 still cites 93.0206(a) and still names the three signers, so the correction you received is the same whichever text governs.

​

LADBS Electrical Plan Check Corrections: What an Engineer Answers and What Satisfies Each

The items on the LADBS Electrical Plan Check Correction List (PC/ELEC/Corr.Lst.08, Rev. 12/01/2022) that an engineer typically answers are A.1 (signature and registration number), A.14 (load schedules), A.24 (single line), E.2 (utility fault current), E.15 and E.16 (service load and Article 220.87), F.6 (short circuit), and W.1–W.2 (Title 24 certificates), and each is answered by a document, not a signature. Find your circled item. Each entry says what the checker wants, what you furnish, what we produce, and where sets usually go wrong. The list is keyed to the 2023 Los Angeles Electrical Code; if LADBS issues a 2026 list, the item numbers may move.

​

“The plans shall bear the signature and registration number of a State of California: Registered Electrical Engineer, or Licensed Architect, or Licensed Electrical Contractor (C-10)” (item A.1)

The checker wants a licensed name and number on every sheet, and the license has to fit the person who prepared the work. You furnish the set as it stands and tell us who drew it and who is installing it. If the two are the same C-10, you may not need us. If they are not, we review the set and sign the sheets we take responsible charge of. The usual mistake is a drafter’s or a lost design-build firm’s title block with no license behind it.

ladbs-electrical-plan-check-los-angeles-permit-requirements.webp

“Provide load schedules for panel boards, distribution boards, motor control centers, and switchboards” (item A.14)

The checker wants a schedule for every panel the work touches, showing each circuit, its load, and the total with demand factors applied. You furnish the existing panel directories, nameplate photos, and the equipment cut sheets for what is being added. We produce the schedules and carry the totals to the feeders and the service. The usual mistake is a schedule for the new panel only, with the existing panel marked “existing” and nothing behind it.

​

“Provide single line diagram not a riser diagram” (item A.24)

A riser shows where conduits go. A single line shows what the system is: service, every overcurrent device and its rating, conductor sizes, grounding, and the ratings the list asks for in items A.17 and A.18, “the voltage drops and available fault current values at each distribution board, panel, ATS” and “the short circuit withstand/interrupting rating of switchboards, panels, ATS, circuit breakers, fuses,” and the equipment ratings in A.25. You furnish the field information: what is there, what is being added, photos of the service and the main gear labels. We produce the single line with ratings. The usual mistake is a riser with equipment names and no numbers.

​

“Provide a copy of the utility’s service report indicating the available fault current, voltage, amperes and phase at the service” (item E.2)

The list adds: “A six-month commitment letter is not allowed.” You furnish the utility’s service report or, where the utility will not issue one for an existing service, the transformer size, impedance, and secondary conductor data from the utility planner. We calculate the available fault current from that data and show it on the single line. The usual mistake is submitting a will-serve or commitment letter, which is exactly what the list refuses. See power system studies for how the fault current study is built.

​

“Provide service load calculation” and “Service and feeder demand load calculation shall be in accordance with Article 220.87” (items E.15 and E.16)

The checker wants to see that the service can carry the new load, and for an existing service that means the existing load has to be established by the method in Article 220.87. That method sizes the existing load from measured demand, not energy: one year of maximum-demand data for the service, carried at 125 percent plus the new load, or, where a year of data does not exist, a recording meter on the highest-loaded phase for at least 30 days while the space is occupied, with the larger of the heating or cooling load added. Twelve months of utility bills satisfy the first method when they show peak demand in kW, as commercial bills on a demand rate do; bills that show only kilowatt-hours are energy, not demand, and satisfy neither. You furnish the bills, the utility’s demand history for the account, or recorded metering. We produce the 220.87 calculation and the service load calculation. The usual mistake is a calculation built from the panel directory with no measured existing load behind it.

​

“Provide short circuit analysis including motor contribution” (item F.6)

The list adds: “Fuse let-thru is not acceptable.” The checker wants the fault current calculated at each piece of equipment, with motor contribution included, and compared to the equipment ratings. You furnish the utility fault current or transformer data from item E.2 and the motor list. We produce the study and the ratings on the single line. The usual mistake is a fuse let-through chart standing in for a calculation. A series rating is allowed, but item F.7 wants the combination rating, the fuse class, the breaker model, and the manufacturer’s sheet on the plans; we put them there. See power system studies.

​

The Title 24 Lighting Certificates of Compliance (Items W.1 and W.2)

The list requires that “the applicable certificate(s) of compliance forms for interior lighting and for outdoor lighting shall be printed on the plans” and that each “shall be completed, signed and dated by the person responsible for its preparation prior to plan check approval.” You furnish the fixture schedule, cut sheets, room areas, and the controls intended. We prepare the lighting compliance forms and place them on the sheets. The usual mistake is a form that lists fixtures without the controls table, or forms left off the plans.

​

Outside this service: hazardous-location classification, fire alarm and emergency systems, work over 1,000 volts, and field metering. If your correction sheet is mostly those items, say so in your email and we will tell you plainly whether it fits.

​

Send the correction sheet, the checked set, the single-line and panel schedules as they exist, any utility letter, and the job address. You get the scope, the turnaround, and the fee after we review what you send. Expedited review is available.

​

jerry@reddog.engineering · (626) 428-9005

los-angeles-ti-07.webp

Other Southern California Jurisdictions: What Each One’s Checklist Says

Who signs depends on the city. Long Beach accepts an electrical engineer, architect, or C-10. Calabasas accepts a registered design professional or licensed electrical contractor. Yorba Linda accepts an engineer or architect. The City of San Diego requires a licensed electrical engineer unless the contractor both designs and installs; Fullerton requires one at 400 amps or 600 volts to ground. LA County accepts an electrical engineer, or the electrical contractor who performs the installation, for load calculations and single-lines. Each entry below quotes the document as it reads and links it. These are the cities’ own words, not a summary; where a city asks for something the state no longer requires, such as a license expiration date (dropped from the seal rule in 2010; BPELSG guide, Q31), the line is quoted anyway because that is what the counter will ask for.

​

Los Angeles County (unincorporated and contract cities)

Plan check required for “installation, alteration, or relocation of electrical equipment rated at 400 Amp or greater” (400 A, 120/240 V single-phase, 3-wire single-family systems excepted), for “tenant improvement installations submitted within twelve (12) months of the approval date of shell building electrical plans,” and “when determined by the Building Official, electrical plans may be required for any electrical installation.” For who signs, the County’s Minimum Plan Submittal Requirements (V1.0, 7/2000) says load calculations and single line diagrams for all commercial/industrial projects “must be prepared by a State of California licensed electrical engineer or State licensed as an Electrical Contractor provided said Electrical Contractor performs the installation.”

​

Source: Electrical Plan Check page; Submittal Checklist, updated 07/06/2020; Minimum Plan Submittal Requirements: Mechanical, Electrical, & Plumbing Permits, V1.0, 7/2000

​

Long Beach

“Each sheet of the construction documents must bear stamp, signature, registration number and expiration date of the Responsible Party. The Responsible Party is the Registered Electrical Engineer, or Licensed Architect, or Licensed Electrical Contractor (C-10).”

​

Source: Electrical Plan Review Checklist V3.1​

​​

Calabasas

Service equipment “400 amperes or larger OR exceeds available fault current of 10,000 amps shall be prepared and stamped by a registered design professional or licensed electrical contractor”; “single-line diagrams shall be stamped by a registered design professional or licensed electrical contractor.”

​

Source: Electrical Plan Check Submittal Requirements, 3/2026

​

Fullerton

“All plans submitted requiring a connected load of 400 or greater amperes, or 600 volts to ground, or greater, shall be prepared by an Electrical Engineer registered by the State of California and each sheet shall bear his registration number, date of expiration and signature.”

​

Source: Fullerton Municipal Code 14.05.030 (adds CEC 89.108.4.1.1; Ord. 3316, 2022)

​

Yorba Linda

“Only plans prepared by or stamped and signed by a State of California Registered Engineer or Licensed Architect, will be accepted for all commercial projects.”

​

Source: Tenant Improvements — Plan Check Requirements

​

Anaheim

“Exception: Mechanical/ plumbing/ electrical plans may be wet-signed by the licensed engineer or a design/build contractor.”

​

Source: Industrial/Commercial/Multi-Family Submittal Requirements, Documents 720 (2018) and 1671

​

San Diego (city)

“The electrical plans and calculations shall be signed by a licensed electrical engineer.” An electrical contractor may sign “only if he/she is responsible for both the design and installation of the system.” Plans are required for buildings other than one- and two-family dwellings unless the work qualifies for a no-plan permit.

​

Source: Plan (required) Electrical Permit

​

San Diego County (unincorporated, PDS)

The County’s “Who May Prepare Plans” form says plans “shall be prepared and each sheet shall be signed by a person licensed by the State of California as a civil engineer, structural engineer, or architect,” and exempts “nonstructural storefronts, interior alterations or additions.” It does not address electrical plans, so the state rule (B&P 6737.3, above) decides who signs them.

​

Source: PDS 118, Who May Prepare Plans, Rev. 09/24/2012​

​​

For the rule in each San Diego County city, see electrical engineer and PE stamp in San Diego County. For the rule in each Orange County city, see electrical engineer and PE stamp in Orange County, California.

​

If you are permitting in a city not listed, send us the correction sheet and we will read it against that city’s checklist.

​

What the Utility Asks For When Service Changes

For commercial, industrial, and large residential service, LADWP’s guide lists a “one-line electrical diagram (two copies) detailing the requested service voltage and all the switch and bus amps” and a “load schedule (two copies) summarizing the service amps and all electrical loads,” along with a site plan and the Service Planning Information Form (LADWP, Guide to Electric Service). The guide also notes that for services other than small residential ones “a fault current value will be calculated on an individual basis and a fault current report will be sent to the LADBS,” which is the report item E.2 asks for.

​

The guide does not say who prepares the one-line or the load schedule. In practice they are the same documents the plan checker wants, with the same numbers on them, and the engineer’s calculation is the practical way to produce one set that satisfies both. Send what the utility planner sent you along with the correction sheet.

​​

When the Answer Is an Engineer

If the person who drew the plans will not be the one installing them, or the checker has asked for calculations, the plans are signed by a registered electrical engineer. Red Dog Engineering does that work remotely and has permitted electrical work with LADBS, Los Angeles County Building and Safety, cities across Los Angeles and Orange counties, most cities in San Diego County, and San Diego County PDS.

​

Send the correction sheet, the checked set, the single-line and panel schedules as they exist, any utility letter, and the job address. You get the scope, the turnaround, and the fee after we review what you send. Expedited review is available. Sealed sheets come back with an electronic seal, which state regulation allows: the seal may be “an electronically-generated representation on the documents” and “the signature may be applied to the documents electronically” (16 CCR § 411(e)), and the Board confirms that engineers “may choose to affix their signature and seals to their documents through electronic means” while noting that “local agencies may adopt ordinances or regulations requiring ‘wet’ stamps and/or signatures” (BPELSG guide, Q32). Where a city asks for wet signatures, as Anaheim’s submittal handout does, we print, wet-stamp, and deliver originals. A certificate of insurance is available on request.

​

jerry@reddog.engineering · (626) 428-9005

​

For the full service, deliverables, and how a review proceeds, see electrical plan review and PE stamp in Los Angeles. If the set is a tenant improvement that still needs design, see tenant improvement electrical plans. If the work is equipment, panels, or feeders in an existing facility, see commercial facility upgrade electrical plans. Design-build contractors who need an engineer of record, see design-build electrical engineering. Design-build shops that draft their own sets, or whose GC requires an engineer of record, can see engineer of record and on-call engineering for design-build electrical contractors.

​

For a house, duplex, or residential unit, this page does not apply; your city’s building department will tell you what it requires for residential electrical permits.

Get a Scope and Fee for the Engineer’s Items

Email the drawings, the single-line and panel schedules as they exist, any utility letter, the jurisdiction, and the job address. We tell you which items need an engineer and what it takes to clear them.

​

Or email directly: jerry@reddog.engineering

FAQ

1. Who is allowed to sign electrical plans for a commercial permit in California?

A registered electrical engineer, a licensed architect, or the contractor who will install the work, within his license classification. The contractor’s allowance comes from Business and Professions Code 6737.3 and does not extend to “work which is to be installed by another person.”

​

2. My LADBS correction says the plans must bear the signature and registration number of a registered electrical engineer, licensed architect, or C-10 contractor. Who do I need?

If the C-10 who drew the set is the one installing it, he signs. If anyone else drew it, you need an electrical engineer or an architect. That is item A.1 of the LADBS correction list, citing LAMC 93.0206(a).

​

3. Can my electrical subcontractor sign the electrical drawings, or do I need an engineer?

He can sign drawings for work his own firm installs. The Board’s guide is specific: “an employee of the contractor may perform the installation. However, the contractor cannot subcontract the installation to another contractor” (BPELSG guide, Q10).

​

4. Can an engineer sign just the single-line and the load calculations and not the whole set?

Yes. The seal covers the work it is placed on. Plans are signed and sealed so that “all work can be clearly attributed to the licensee(s) in responsible charge” (16 CCR 411(g)(1)), with a notation describing the work under each licensee’s charge where more than one signs (411(g)(3)). The engineer seals the single-line, the schedules, and the calculations he produced or reviewed, and the sheets say so.

​

5. Do electrical plans need to be stamped by an engineer in California?

Only when the person who prepared them is not the contractor installing them, or when the city requires engineering calculations the contractor exemption does not cover. If yours do, see electrical plan review and PE stamp in Los Angeles.

​​

6. Who can stamp electrical plans in California?

A California-registered electrical engineer, for the work in his responsible charge. For how that review works and what you receive, see electrical plan review and PE stamp in Los Angeles.​

​

7. Is an electronic seal accepted on electrical plans in California, or does it have to be a wet stamp?

The state allows an electronic seal and signature (16 CCR 411(e)), and the Board says so (guide, Q32) while noting a city may require wet stamps. Anaheim’s submittal handout says “wet-signed.” We seal electronically and wet-stamp originals where a city asks.

​

8. The plan checker wants the existing load per Article 220.87. Will the utility bills work?

They will if they show demand. Article 220.87 sizes the existing load from measured maximum demand: one year of it for the service, carried at 125 percent plus the new load, or, where a year of data does not exist, a recording meter on the highest-loaded phase for at least 30 days while the space is occupied, with the larger of the heating or cooling load added. Commercial bills on a demand rate print each month’s peak kW, and twelve of them cover the year. A bill that shows only kilowatt-hours is energy, not demand, and does not. Send the last twelve bills or the utility’s demand history for the account; if neither shows peak demand, have a meter set. We do the calculation from any of them.

​

9. The plan checker wants a utility fault current letter and the utility won’t issue one. What satisfies the correction?

LADBS item E.2 asks for the utility’s service report with available fault current, and says “a six-month commitment letter is not allowed.” Where no report exists for an existing service, we calculate fault current from the utility transformer data you obtain. See power system studies.

​

10. When does LA County require an electrical plan check?

Among other cases, for “installation, alteration, or relocation of electrical equipment rated at 400 Amp or greater” (except 400 A, 120/240 V single-phase, 3-wire single-family systems), tenant improvements submitted within twelve months of the shell building’s electrical plan approval, and “when determined by the Building Official” (LA County Electrical Plan Check).

​

11. Does the engineer need to visit the site to sign the plans?

No. The regulation allows the engineer to “review and approve through the use of communication devices” (16 CCR 404.1(a)(3)). You furnish the field information, photos, and nameplates; the review is done from them.

​

12. How fast can this be done and what does it cost?

You get the scope, the turnaround, and the fee after we review what you send. Expedited review is available. Send the correction sheet and the checked set to jerry@reddog.engineering or call (626) 428-9005.

​

Sources

Reviewed November 2, 2026

 

Every rule on this page is cited to one of the documents below.

 

Jerry Poon, PE, California #20878 — verify at the Board’s license lookup.

 

jerry@reddog.engineering · (626) 428-9005

Electrical Plans Reviewed and Signed by a California PE

For contractors and project teams in Los Angeles, Orange, and San Diego counties. Red Dog Engineering reviews what you send and returns a proposal with the scope, deliverables, fee, and turnaround. Expedited review is available.

​

  • Review and signature on contractor-prepared electrical plans

  • Load calculations, panel schedules, and single-line diagrams

  • Article 220.87 existing-load and service load calculations

  • Fault current and short-circuit studies for LADBS items E.2 and F.6

  • Title 24 lighting compliance forms placed on the sheets​

Or email directly: jerry@reddog.engineering

About the Engineer

Red Dog Engineering is Jerry Poon, PE, California Electrical Engineer License #20878 (verify at the Board). Jerry has 15+ years of experience in MEP engineering, electrical design, and permit-driven commercial work. He reviews and signs electrical plans for contractors and project teams across Los Angeles, Orange, and San Diego counties, working remotely from drawings, calculations, and field photos.

​

Before he seals a set, he reviews the engineering behind it and marks up what has to change, so the plans, panel schedules, and calculations agree. He stays the engineering contact through the plan-check responses covered by the agreement.

bottom of page